I have run the project economics using public information available. For the Low Case, I calculated an IRR of 9.21%. For my Base Case, I calculated an IRR of 10.66% (Below is a list of my assumptions and data sources). I believe the project has substantial upside potential and little downside risk.
- The 2.4 billion project cost may be high. Some sources have reported only $2 billion (Just for the heck of it I ran the economics at 2 Billion instead of my assumption of 2.4 billion and got an IRR of almost 15%).
- The PPA is reported at $.015 per kilowatt hour. Most of these PPAs have escalators associated with them. If MidAmerica was able to negotiate a PPA in which the spread between PPA revenue and O&M cost increases over time, the project will return a higher IRR than I have calculated
- It quite possible that the efficiency factor is greater than the 20-25% that I have assumed. Again this produces upside potential
- I have assumed an effective tax rate of 45% which may be high
The reasons that the economics work for this project are:
- 30% tax credit for MidAmerica when the project begins operations
- The PPA with PG&E that assures:
- A home for the energy produced for the life of the project
- A price for the energy which could only be achieved with the help of the State of California's Renewable Portfolio Standards law (Watch for an upcoming blog that describes in detail RPS which is in essence a back door method to achieve the goals of Cap and Trade).
Assumptions
- Total Project Cost 2.4 Billion
- Source: Topaz Solar Farm Revised CUP – website as follows:
- 1.2 Billion Financed at 5.75 %
- Loan amortized over 25 years
- Level payments of 91.69 per year (my assumption, actual may be different)
Source: NREL article – website https://financere.nrel.gov/finance/content/midamerican-solar-thin-film-utility-scale-project-Topaz-550-MW-megawatt-bond-financing
Note Details of finance not fully described
- PPA
- Done deal with PG&E
- $150/MegawattHr - (.015/kwh)
- 25 Years
Source: NREL article
Note: PPAs generally have an escalator based upon inflation. I have chosen to ignore the escalator and ignore the escalator in O&M costs shown below
- O&M Costs
- Contract caps at $16.5 million/yr with escalator for inflation
Note: this figure is far below O&M costs estimated for solar PV projects estimated by DOE in its Renewable LEV Report
Construction risk low because of E&C contract – NREL article
- Efficiency Factor
- Revised CUP document pegs at 20.76% (page 12 “project will deliver on average over 1 million megawatt hours/yr). I have used this efficiency factor for the low case
- DOE report on renewable LEV indicates a 25% factor. I have used this in the base case scenario
- I have assumed that for tax purposes the entire project is written off on a 5 year basis from time of start up
- I have assumed a 45% effective tax rate (35 Fed, 10 California). I am not at tax expert, so I assumed the worst case scenario. The actual effective tax rate may be lower.
- 30% federal tax credit taken in year of start up (based on 2.4 Billion Investment)
No comments:
Post a Comment